Lot 1, the only things pending are utitlities and approval from Los Altos Hills. Over the next few weeks we'll be completing punch list items on the interior, scheduling and coordinating final inspections, and wrapping up the last of the landscaping.
Lot 2 and lot 3, concrete driveway is now poured. Interiors for both of the homes are approximately at the same stage. We are pushing to have both interiors and exteriors complete by the end of this month.
Once again Lot 2 is in contract and will close upon occupancy certificate. For Lot 3, we have a stageing date at the end of this month in order to bring the property to market.
On all three lots, PG&E remains the longpole in getting occupancy cerrtificate, and we are doing evertyhing we can to expidite the process.